Thursday, June 6, 2013

Scana delays start of new S.C. nuclear reactor by months | Reuters

In a presentation, Scana said Unit 2, which was expected to enter service in March 2017, will instead likely enter service between the fourth quarter of 2017 and the first quarter of 2018.
Scana said this was due in part to delays in delivery of some components from a unit of construction contractor Chicago Bridge & Iron Co NV (CB&I) from its Lake Charles, Louisiana facility