Docket No. 2005-83-A: Commission Directive regarding Notices of Filing and/or Hearing Served on Behalf of the Commission Containing Company Logos and/or Copyright Notations

"Commission Notices of Filing and/or Hearing provided to ratepayers on behalf of the Commission by our regulated companies have sometimes contained company logos and/or copyright notations. Going forward, Commission Notices of Filing and/or Hearing served on behalf of the Commission by regulated companies are not to contain company logos and/or copyright notations."

Scana delays start of new S.C. nuclear reactor by months | Reuters

In a presentation, Scana said Unit 2, which was expected to enter service in March 2017, will instead likely enter service between the fourth quarter of 2017 and the first quarter of 2018.
Scana said this was due in part to delays in delivery of some components from a unit of construction contractor Chicago Bridge & Iron Co NV (CB&I) from its Lake Charles, Louisiana facility

SCE&G to accelerate shutdown of two coal units near Walterboro – The Post and Courier

 BY WARREN L. WISE
wwise@postandcourier.com

Accelerating its shutdown schedule for aging coal-fired power units, South Carolina Electric & Gas Co. announced Tuesday it will snuff out two units at its Canadys Station power plant near Walterboro by Dec. 31, four years ahead of schedule.

Monday, June 3, 2013

Phishing robocall $100 bonus | Verizon Wireless Community

Here's a screenshot of the mybonus100.com site.  You have to look at the URL in the address bar to tell that it isn't the verizonwireless site, and if you just got a call purporting to be from verizon telling you to log into that site you might think that's ok.  A whois lookup of the mybonus100.com domain name shows that it was only registered yesterday, 5 May 2013, the same day I got the first call. 